    Site-to-Opening

    Carry a market opportunity from site search through approval, lease, design, construction and fit-out to a store that opens on time, trades and is reviewed against the case that justified it. Where Shelf-to-Basket (VS-110) runs an existing store's trade, this changes the network itself; remodels and relocations re-enter at Approve the Case, and closures are decided at Review the Store.

    • New Store Opening
    • Store Development Lifecycle
    • Real Estate-to-Trade
    // FIG. 03 · Stage flow
    1Find the Site2Approve the Case3Secure the Lease4Design & Build5Staff, Stock & Op…6Review the Store
    1. 01

      Find the Site

      VS-340.10

      Identify the market gap, analyze candidate trade areas and estimate sales and cannibalization of nearby stores.

    2. 02

      Approve the Case

      VS-340.20

      Put the site, format, capital and forecast to the investment committee and win approval.

    3. 03

      Secure the Lease

      VS-340.30

      Negotiate and sign the lease or purchase, with zoning and land-use approval as a contingency.

    4. 04

      Design & Build

      VS-340.40

      Adapt the format prototype to the site, obtain building permits, build and install fixtures, systems and security, and obtain the certificate of occupancy.

    5. 05

      Staff, Stock & Open

      VS-340.50

      Hire and train the team, receive the opening assortment, pass readiness checks and open to customers.

    6. 06

      Review the Store

      VS-340.60

      Compare trading with the approved case, decide on adjustments, and feed the lessons into the next site and the remodel or closure pipeline.