Turn a forecast need, a regulatory commitment or a queue of connections into new or reinforced network assets in service, with their cost approved and recovered through rates, a price control or tariffs. Where Acquire-to-Retire (VS-210) follows any asset through its life, this stream runs from network planning through regulated cost recovery.
- Plan-to-Build
- Capital Delivery (Utilities)
- Network Investment Lifecycle
- Plan-Build-Energize
- 01
Forecast Need
VS-260.10Project load, generation and water demand by area and find where and when the network will fall short.
- 02
Choose the Solution
VS-260.20Compare building, non-wires alternatives and flexibility, and pick the option with the best cost and risk over the asset's life.
- 03
Plan & Seek Approval
VS-260.30Place the project in the regulated capital plan and win approval for it in the rate case or price control.
- 04
Design & Build
VS-260.40Design the works, secure rights and permits, buy materials and services, and build to the design.
- 05
Commission & Energize
VS-260.50Test, energize and hand the new assets to operations, with the network records and asset register updated.
- 06
Recover the Cost
VS-260.60Report the spend and outcomes to the regulator and bring the asset into rates or allowed revenue.