    Transmission Outage Coordination

    Plan and approve outages of transmission lines and substations so work can go ahead without leaving the system insecure, coordinated with neighboring owners and the reliability coordinator.

    • Outage Coordination
    • Transmission Outage Scheduling
    • Planned Outage Approval

    In scope

    • Outage requests for transmission equipment
    • Outage studies against expected conditions
    • Coordination of outage timing with neighbors and the coordinator

    Out of scope

    • Scheduling the maintenance work itself (see BC-680.20.40)
    • Carrying out the switching and clearances for an outage (see BC-1590.10.40)