{"version":"0.12.1","built_at":"2026-10-12T10:56:26.035Z","license":"CC BY 4.0 © Mike Reams","canonical":"https://catalog.mikereams.com","capability":{"id":"BC-1520.20.10","name":"Pre-Energization Testing","level":3,"parent_id":"BC-1520.20","l1_id":"BC-1520","industry":"utilities","macro_id":null,"path":["Network Construction & Field Work","Network Commissioning & Energization","Pre-Energization Testing"],"description":"Test insulation, protection settings, phasing and earthing on new equipment and record the results before it goes live.","aliases":["Commissioning Tests","Acceptance Testing"],"in_scope":[],"out_of_scope":[],"csdm_note":null,"status":"active","successor_id":null,"child_ids":[]},"crosswalk":{"realized_by":[],"used_in":[],"patterns":[],"stacks":[],"books":[],"technology":[]},"ancestors":[{"id":"BC-1520","name":"Network Construction & Field Work","level":1},{"id":"BC-1520.20","name":"Network Commissioning & Energization","level":2}],"children":[]}